The final stage of Glenview Park Estate, Stage 8, has commenced civil construction. This is the last stage of the 238 lot residential subdivision located in Wauchope, Yippin Creek.
The developer and project manager for the estate has been Glenview Wauchope Pty Ltd. King & Campbell Pty Ltd have been the lead consultant on the project, providing town planning, urban design, surveying, civil engineering, landscape architecture, and technical assistance services. J Newton Civil Construction Pty Ltd have been the lead civil contractor for all stages.
Stage 1 (28 lots) of Glenview Park Estate commenced construction in 2014, and the demand for new housing lots in the estate has not slowed down since. The residential subdivision proceeded in the following stages:
Stage 2 - 48 lots
Stage 3 & 4 - 58 lots
Stage 5 & 6 - 52 lots
Stage 7 - 23 lots
Stage 8 - 29 lots